UPDATED: 6/26/23
CLARK COUNTY, Ind.— The Indiana Department of Transportation announces an added travel and turn lanes project to begin at the intersection of State Road 60 and Poindexter Lane in Clark County.
Beginning on or after Monday, March 6 crews will begin phase one of the project which includes the installation of signs, striping, and barrier wall. This phase is expected to last through May of this year. Impacts to traffic include:
- Shifting traffic on S.R. 60 each direction into two 10′ travel lanes
- Reducing the speed limit on S.R. 60 through the project area to 40 mph
- Closing Poindexter Lane at S.R. 60 on or after Thursday, March 16 until both phases of the project are completed.
The detour route for Poindexter Lane will utilize Newberry Road.
Phase two of the project includes construction of underdrains, curb/gutter, and new asphalt. Work is expected to be complete in late summer. The contract was awarded to E&B Paving Inc. for $2.2 million.
INDOT encourages drivers to consider worker safety by slowing down, using extra caution and driving distraction-free in and around all work zones. All work is weather-dependent and schedules are subject to change.
About the Indiana Department of Transportation
INDOT continues to solidify the Hoosier State as the Crossroads of America by implementing Gov. Eric J. Holcomb’s $30 billion Next Level Roads plan. With six district offices and 3,500 employees, the agency is responsible for constructing and maintaining more than 29,000 lane miles of highways, more than 5,700 bridges, and supporting 4,500 rail miles and 127 aviation facilities across the state. INDOT was recently ranked #1 in the United States for infrastructure in CNBC’s 2022 “America’s Top States for Business” ranking. Learn more about INDOT at in.gov/indot.